New Shepparton Art Museum - Project Update for September

The first level concrete pour was completed on 19 September with 400 cubic metres of concrete and 10 tonne of steel involved.

Construction works completed:

  • Ground floor services and concrete
  • Building core and column verticals
  • Level 1 concrete deck

Construction works commenced:

  • Stormwater drainage

Construction works coming up:

  • Demolition of the caravan park residence
  • Level 2 formwork and concrete pour
  • Level 2 vertical formwork and concrete pour
  • Loading dock vertical walls formwork and pour

For the latest update video please visit the new SAM project webpage.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.