Work resumed last month on public pool upgrades in Bombala and Cooma. As part of our commitment to providing monthly community updates, Council is reporting on what's been done over the past four weeks, what we're working on now, and what's coming up.
June 2026 Progress Report: Bombala and Cooma public pool upgrades
What we've been doing this past month
Cooma Pool
- Heat pump slab complete
- Loading dock and stairs complete
- Emergency exit stairs and path complete
- Survey works for power pole anchor cable
- Contract plumber engaged
- Contract electrician engaged
- Plumbing work started
- Driveway and tie-in to Crisp Street complete
Bombala Pool
- Contract plumber engaged
- Contract electrician engaged
- Plumbing work started
- Site clean-up completed
- Pool lip reduction redesign commenced, $30,000 budgeted for options and costings
- Cr Stewart, Cr Hopkins and pool user group form new Bombala Pool Advisory Group
What we'll be doing in the month ahead
Cooma Pool
- Securing approval for power pole anchor cable relocation
- Continuing contractor quote evaluations
- Finalising remaining trade and supplier contracts
- Concreting
- Plumbing
- Electrical work
- Further drainage repairs to pits damaged by stormwater
Bombala Pool
- Continuing contractor quote evaluations
- Finalising remaining trade and supplier contracts
- Concreting
- Plumbing
- Electrical works
Visit https://qrco.de/SMRCprojects for the latest project updates
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.