December Production Plan

We at Toyota would like to again apologize for the repeated adjustments to our production plan due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers, who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.

The planned global production volume for December is expected to be approximately 750,000 units (approx. 250,000 units in Japan and 500,000 units overseas).

As for the full-year production forecast for FY2023, we have taken future risks such as the shortage of semiconductors into account and announced 9.2 million units.

We will continue to closely examine the supply of parts and work with related parties to consider all possible measures to ensure that we can deliver as many vehicles to our customers at the earliest date.

The following is the revised domestic operations suspension schedule for December.

Suspension of production in December (4 lines in 3 plants out of 28 lines in 14 plants)

PlantPeriod of production suspensionProduction model
Toyota Motor Corporation

Takaoka Plant

Production line #2December 2 (Fri), 9 (Fri) RAV4, Harrier
Toyota Motor Corporation

Tahara Plant

Production line #1December 1 (Thu), 2 (Fri), 9 (Fri), 16 (Fri) Land Cruiser Prado, Lexus GX, 4Runner
Toyota Motor Kyushu

Miyata Plant

Production line #1December 28 (Wed)Lexus NX, NX450h+, ES, UX, UX300e
Production line #2Lexus ES, RX
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.