The much-anticipated Myall River dredging project has been completed.
The dredge was finishing the connection of the eastern channel to the deep water in the port last week.
MidCoast Council is happy to advise that there were no major delays.
A total of 132,300m3 of sand was removed from the Eastern Channel, Corrie Channel and from the Myall River. Not only will this make boating navigation safer, it will also improve the flows and tidal movements in the estuary leading to better water quality.
The dredged sand has been stockpiled at Winda Whoppa, allowing for future renourishment of Jimmys Beach.
The contractor – Dredging Solutions will spend the following coming week removing the equipment from the site.
While Council managed this major project it was fully funded by TfNSW.
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.