City Of Adelaide's Staged Main Streets Program

A staged program of detailed design, procurement and capital works has been incorporated within the 2026/27 Business Plan and Budget to progress Council's five main street projects.

Council remains committed to the long-term revitalisation of our five main streets - recognising their importance as centres of economic activity, community life and cultural expression.

Starting with the installation of two Melbourne Street wombat crossings, the staged works will also deliver a revitalised Gouger Street, Hutt Street, O'Connell Street and Hindley Street.

Significant groundwork has already been undertaken to support this goal, including developing design concepts, engaging with the community, contractor procurement, and actively pursuing external grant funding opportunities.

The Lord Mayor said the approach to the timing of main street projects is guided by a clear principle - delivering high-quality outcomes while maintaining the day-to-day functionality of the city during construction.

"We recognise that upgrading all main streets at once would place significant pressure on traffic movement, local access and business activity," said the Lord Mayor.

"Instead, Council has adopted a carefully sequenced rollout of projects that minimises disruption and supports continued access to businesses and services. Importantly, it ensures the city remains accessible and operational throughout the works program.

"Our planned main streets program is crucial for the city and North Adelaide, but no one wants the place to come to a standstill while we carry out these works, so we have made a sensible decision.

"A considered and balanced approach has been taken to determining the sequencing of main street projects, ensuring each stage can deliver the strongest benefit to the community."

Works will align project timing with construction industry capacity and State and Commonwealth funding opportunities to maximise external investment and reduce pressure on ratepayers.

Coordinating works with major private developments will minimise disruption and deliver cohesive outcomes while prioritising upgrades that improve public safety and accessibility.

Together, these factors guide well-timed, high-quality improvements that enhance the usability, comfort and overall experience of each main street while ensuring efficient and responsible use of public funds.

Through this logical staged delivery approach, Council is reinforcing our commitment to revitalising city and North Adelaide main streets - delivering enduring benefits for businesses, residents and visitors, while ensuring value for money and a city that continues to function and thrive throughout the transformation.

The following work will be progressed on our five main streets this financial year:

Main Street

2026/27 Planned Work

Target Project Completion

O'Connell Street

  • Completion of detailed design work
  • Contractor procurement
  • Commencement of capital works
Q3 2028/29

Gouger Street

  • Finalise detailed design and contractor procurement
  • Commencement of capital works
Q1 2028/29

Melbourne Street

  • Installation of wombat crossings
  • Commence detailed design work
Q3 2029/30

Hutt Street

  • Finalise detailed design work
  • Contractor procurement
  • Commencement of capital works
Q1 2028/29

Hindley Street

  • Pursue grant funding opportunities
  • Commence detailed design work
Q4 2029/30
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.