Works are progressing on the Darraweit Road upgrade in Wallan, with underground drainage now well underway along the section between Acacia Way and Roulston Way.
The upgrade is part of the Australian Government's $11 million commitment to road upgrades in the Macedon and Mitchell Shires, with $5.5 million allocated across the Darraweit Road and Wellington Street projects. Mitchell Shire Council has also committed $200,000 towards these upgrades.
The project will deliver underground drainage, kerbing and full reconstruction of the road pavement to improve safety and durability for road users.
Since construction began in April, drainage trench excavations have continued throughout the site.
However, crews have encountered rock beneath the surface, which has caused some delays to the initial schedule.
Despite this, works are continuing, and the project remains on track for completion in October, weather permitting.
Construction of a new retaining wall is scheduled to begin soon and will continue throughout August.
We thank the community for their patience while these important works are carried out.
Visit the project page for ongoing updates.