ACT Greens Leader Jo Clay has called on the ACT Labor Government to urgently explain how the Digital Health Record (DHR) has grown from an original business case of $213.8 million to a reported total cost of over $500 million.
In Annual Report hearings this morning, officials told the Committee that total DHR costs to date are over $500 million. They suggested part of the difference 'may be operating costs not included in the original business case' and that 'they are still checking figures'.
"The same week Canberrans are being told that 18 public schools are facing budget cuts, a single IT project has grown to more than twice the cost the Government first told us it would be.
"If a significant part of this blowout is operating costs that were never included in the business case, this means that the Government asked the public to back a project without telling them its true long-term cost.
"The problems were identified years ago. A KMPG review in August 2024 found the project was delivered with ineffective financial management and cost control and had no contingency allowance.
"The DHR's procurement is also under scrutiny from the ACT Integrity Commission through Operation Marram, and the Auditor-General has examined the project's invoicing and payments.
"It is appropriate that the Integrity Commission and the Auditor-General are able to do their work, and I won't pre-empt their findings. The community deserves answers about a project this size, with this many red flags.
"The warnings were there, yet the Government failed to get a grip on forecasting and cost control throughout the life of this project.
"While paramedics, nurses, allied health workers, doctors, among many other public servants are being told to do with less, the people of Canberra simply cannot afford lax financial management from the Government," said Ms Clay.
Background for journalists:
- In 2025, in response to a question taken on notice from Ms Clay (SP QTON 069), the Health Directorate confirmed the 2019-20 revised business case of $213.8 million against an eight-year program cost of $378.2 million, an overspend of about $164 million. Today's figure suggests the true cost is far higher again.
- Some relevant key findings from the 2024 KPMG review include 'poor cost estimation accuracy', 'necessary financial management processes were not in place to ensure costs risks were managed' (page 9) and that 'the removal of contingency together with decisions to add to program scope...added significant financial risk' (page 31).