Works begin next week on the first stage of a $58 million investment in critical upgrades to the City's sewerage network in Southport, starting at the Broadwater Parklands.
The Southport Major Sewer Upgrade Project will renew around three kilometres of the city's largest sewerage pipeline over several years, strengthening a network that supports more than 600,000 residents and businesses across the Gold Coast.
The Broadwater Parklands component begins next week and will see approximately 1.5 kilometres of major sewer pipeline renewed beneath the ground and will take approximately a year to complete.
Mayor Tom Tate said investing in critical infrastructure was essential to maintaining the lifestyle and liveability the Gold Coast is known for.
"As our city continues to grow, we need to keep investing in the infrastructure that supports all of us," Mayor Tate said.
"Most people never see this infrastructure, but it is absolutely essential. These upgrades will help ensure reliable sewerage services for decades to come while supporting future growth across our city.
"The Broadwater Parklands is one of the Gold Coast's most loved community spaces, and we're using innovative construction methods to minimise impacts while delivering a project that will benefit residents for generations."
The project will replace ageing sections of major sewer infrastructure installed during the 1970s and 1980s and improve the reliability, resilience and flexibility of the city's sewer network.
To reduce disruption to parklands users and the surrounding community, most of the new pipeline beneath the Broadwater Parklands will be installed using trenchless technology, significantly reducing the need for widespread excavation.
The works include the construction of a 1.4km long continuous tunnel 30m deep below the Broadwater parklands.
At approximately 1.5m in diameter this will be one of the largest tunnels of this type in Australia. The full length of pipe will be assembled at Doug Jennings Park before being floated across the Broadwater and installed in position.
While every effort will be made to minimise impacts, some temporary disruptions will be unavoidable during construction.
Residents and visitors may experience periods of construction noise, traffic management changes and increased activity in work areas.
Noise mitigation measures, including acoustic barriers where practical, will be used to reduce impacts.
The City is working closely with the Broadwater Parklands events team to minimise disruption to community events and activities wherever possible.
Once complete, all permanent infrastructure will be located underground and affected areas of the Broadwater Parklands will be restored for the community to enjoy.