Kew Recreation Centre August 2026 Progress Report

Construction update

Construction is progressing well. This month, the following work was completed or started:

Sports courts

The timber flooring is now installed, and court line markings are being applied. Work on the amenities is also moving ahead, with wall and floor tiling complete.

Warm water pool and spa, quiet studio and consult suites

Wall tiling is now finished, and pool tiling will start soon.

25 metre and learn-to-swim pools

Roof installation is complete.

Leisure pool, aqua play area, change rooms and party room

Structural steel is complete, and services installation and roofing is now underway.

Foyer and creche

The roof is now complete. Installation of services and plaster is underway.

Fitness and gym areas

Steel structure installation has started.

Car park

Work on the car park is continuing.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.