Kew Recreation Centre June 2026 Progress Report

Construction update

Construction is progressing well. This month, the following work was completed or started:

Sports courts

The internal wall linings are finished, and windows are in place on the north and west sides. The timber sports court floors are prepared, and flooring installation has started.

Exterior

Work is continuing on the outside of the building, mainly on the southern side and cladding areas.

Changerooms

Inside, wall tiling has started in the change rooms.

Warm water pool and spa, quiet studio and consult suites

Wall, ceiling and skylight sheeting is continuing, and the ceiling lining has commenced.

The outside windows are installed. Internal windows will be installed soon.

Foyer and creche

Structural steel installation has been completed.

Carpark

Preparation work is continuing.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.