Kew Recreation Centre To Open In Mid-2027

One of the most common questions we hear from our community is, "When will Kew Recreation Centre reopen?" We know how important this facility is, and we understand the concerns caused by ongoing delays.

The project team expects construction to be finished in May 2027. Following this, our leisure and aquatic operator, The Y, requires about six weeks to prepare the centre for reopening.

We now expect Kew Recreation Centre to reopen to the public in July 2027.

The unforeseen steel roof collapse, along with the investigations and legal proceedings, significantly impacted the redevelopment timeline.

The decision to change to an all-electric heating source instead of gas boilers made at the Council meeting on 30 June 2025 also delayed the original program.

We're taking every necessary step to ensure the project is completed safely and to a high standard.

We've published a detailed FAQ on the project web page. If you have a question, you can email [email protected]. We'll respond where we can, but we may not be able to answer if your question relates to ongoing legal actions. We'll continue to provide updates as they become available.

We also encourage you to sign up to our mailing list for updates as construction progresses.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.