We at Toyota have made repeated adjustments to our production plans due to a parts shortage resulting from the spread of COVID-19, causing considerable inconvenience to our customers and other parties concerned. We would like to express our gratitude to everyone involved for their immense support in helping us maintain production.

Our global production plan for March 2022 is expected to be around 950,000 units. We had initially factored in recovery from previous production cutbacks, but due to the impact of semiconductor shortages, we have adjusted our production plan by around 100,000 units globally. (Previous single / Full month record high: March 2012, approximately 870,000 units)

The full-year production forecast for the fiscal year ending March 31, 2022, is expected to be approximately 8.5 million units.

With regards to the shortage of semiconductor-related parts, we will continue to examine the situation and consult with all companies involved in considering the use of substitutes where possible in anticipation of a continuing shortage. We will also continue to work with our suppliers in strengthening the supply chain and make every effort to deliver vehicles to our customers as soon as possible.

The following is the schedule for the suspension of domestic operations in March due to the plan revisions. We would like to offer our sincerest apologies to our customers and suppliers for the various inconveniences these adjustments may cause.

Production suspension in March (3 lines in 2 plants out of 28 lines in 14 plants)

PlantsPeriod of production suspensionProduction vehicle
Toyota Motor Kyushu

Miyata Plant

Production line #1March 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 12 (Sat), 14 (Mon), 15 (Tue), 16 (Wed), 19 (Sat), 21 (Mon), 22 (Tue) NX, NX PHV, CT, UX, UX300e
Production line #2March 4 (Fri), 12 (Sat), 19 (Sat) ES, RX
Toyota Motor East Japan

Iwate Plant

Production line #1March 5 (Sat)C-HR, Aqua

Note
Saturdays are a single shift operation.
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.