Pavement and Bulk Earthworks - Windellama Road Stage 5

Goulburn Mulwaree Council

Windellama Road Stage 5 works.png

Goulburn Mulwaree Council advises that works will soon commence on Stage 5 of Windellama Road rehabilitation under Roads to Recovery and Fixing Local Roads funding.

Works will involve pavement rehabilitation, curve realignments and major drainage upgrades along the below sections of Windellama Road over the next 18 months, weather permitting.

In total $4.1M worth of road upgrades will be undertaken with $3M State and $1.1M Federal and Council Funding.

Works will be undertaken over 3 sections with indicative timeline as below.

Section 1

Elouera Lane to Fernleigh Close

2.3 kms

September 23- December 23

Section 2

Fernleigh Close to RA 3188

2.0 Kms

February 24- April 24

Section 3

RA3188 to Lumley/Windellama Rd Intersection

2.2 Kms

September 24- December 24

Section 1 works from Elouera Lane to Fernleigh Close will begin early September 2023 and continue through to December 2023. These works will involve bulk earth works, pavement formation, drainage and pavement works.

Works are scheduled to take place Monday to Friday from 7am - 5pm.

Please be advised that there will be an increase in construction traffic during this time, with Traffic Control measures in place.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.