Construction of the new Rossys Creek Bridge on Corrowong Road is progressing well, with the project team working hard to open the bridge to traffic in early September, weather permitting.
Recent wet weather has caused some delays to the construction of footings and abutments. The project is moving forward now that this important foundational work is complete, with the remaining work less susceptible to weather delays and interruptions.
The bridge replacement is now entering its major construction phase, with structural formwork currently being completed.
These visible milestones will mark significant progress towards the completion of the new bridge, which will provide a safe and reliable creek crossing for Corrowong Road users over the long term.
Council appreciates the community's patience while these works are underway.
Motorists are reminded that Corrowong Road is closed at Rossys Creek Bridge. The detour via Browns Camp Road will remain in place until the new bridge is open to traffic.
For the latest updates on the Rossys Creek Bridge replacement and other Council projects, visit Council's website or follow Snowy Monaro Regional Council on Facebook.