Roadworks continue this month on Myack Street and Park Street, as part of Berridale drainage upgrades.
All work will be complete and both roads fully reopened by Tuesday 18 August 2026, weather permitting, as previously advised. Park Street will no longer be reopening early.
Park Street is open to local traffic only and the Park Street/Myack Street intersection is closed to all traffic.
Myack Street is closed for roughly 70 metres from Jindabyne Road past the Park Street intersection.
Visit https://qrco.de/BerridaleRoads26 for a map of the closure areas.
Heavy vehicles are required to detour via Boundary Street and Jindabyne Road. Cars and other light vehicles can detour via Bolton Street and William Street.
Essential information
What: Road closures
Where: Berridale
Closure 1: Approx. 70 metres of Myack Street from Jindabyne Road intersection
Closure 2: Park Street open to local traffic only, Myack Street intersection closed
Started: Monday 29 June 2026
Duration: Until Tuesday 18 August 2026, weather permitting
Reason: Construction of new under-road creek culverts and related roadworks
Part of Council's ongoing Berridale Village Master Plan project, these works will improve drainage and assist in mitigating the effects of flooding and severe wet weather.
Council appreciates the community's patience during this expanded road closure.