MARYBOROUGH OUTDOOR POOL

Pool-Graphic.jpg(PDF, 172KB)

Detailed designs for stage two and stage three of the project are currently underway and will be completed by 30 June 2026.

Using the funding already secured, it is anticipated that stage two will be delivered in 2026 and 2027.

The detailed designs will give us a clearer understanding of how much the project will cost in its entirety.

Given the size and complexity of the project, we anticipate that there is a shortfall in funding to deliver stage three of the project which includes the 50-metre outdoor pool.

We are actively advocating to the Victorian Government to secure the additional funding needed to complete stage three.

We extend our thanks to the Friends of the Maryborough Outdoor Pool Precinct, who continue to collaborate with us and advocate strongly for this project.

We remain focused on delivering a facility that honours its heritage, supports long-term sustainability, and provides lasting value to our community.

Stage One: Completed

Rebuild of the Octagonal Toddlers Pool, extensive pavilion infrastructure preservation works and pump room repairs. The funding was also used for design and documentation – required in order to pursue funding applications and carry out future works.

Stage Two: Current Stage

Detailed designs underway and will be complete by 30 June, 2026. It is anticipated that stage two will be delivered in 2026 and 2027.

Stage two includes:

■ Full replacement of the intermediate/learn to swim pool including new filtration system and balance tank, renovation of the tiling and shell and construction of a disability access ramp.

■ Upgrade to pavilion to accommodate a new compliant entry with ticketing, kiosk, car parking, footpaths, ramps and landscaping.

■ New change room facility – a new standalone building including family change rooms, accessibility and a changing place facility.

■ Plant room structural repairs.

■ Upgrades to the existing male and female changerooms including new toilets, showers.

■ Upgrades to services at the site including power and sewer.

Stage Three: Future Stage

Detailed designs underway and will be complete by 30 June, 2026. The delivery of stage three is dependent on external funding.

Stage three includes:

■ Demolition and rebuild of 50 metre pool

■ New concourse

■ New filtration system and balance tank

■ Footpaths connecting all areas

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.