Williamson Street Footpath Works

The Williamson Street footpath renewal is part of the City Centre Tree Interactions project. We're committed to repairing our road infrastructure due to the damage of existing tree roots.

Scope of works

The works will occur on the north-east side of Williamson Street, Bendigo, between Myers and Mollison Streets.

It will include new tree pits, concrete kerb, and standard city centre asphalt and bluestone paved footpath. There will be a total number of six carspaces constructed (with a loss of 3 existing carspaces).

Tree removal and new planting

Three existing trees, Plantanus x acerifolia (London plane tree) will be removed and replaced with four Zelkova serrata (Japanese elm) with improved conditions for tree growth.

Funding

The City Centre Tree Interactions project is funded by the City of Greater Bendigo.

Timeline

The works are anticipated to commence mid-January 2026 and be completed by June 2026.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.