Hastings Point Wastewater Treatment Plant - the project will now move to the planning approval phase.
Tweed Shire Council has taken a major step towards securing reliable, environmentally responsible wastewater services for the Tweed Coast, with Councillors voting to progress Option 4 – Advanced Intermittent Process (AIP) for the Hastings Point Wastewater Treatment Plant (WWTP) performance upgrade.
The plant services around 12,860 residents and visitors across Cabarita Beach, Bogangar, Hastings Point and Pottsville. The upgrade will fix existing reliability challenges, meet strict NSW Environment Protection Authority (EPA) licence limits and cater for busy holiday peaks.
Tweed Shire Mayor Reece Byrnes said the decision followed more than 2 years of detailed engineering investigations and community consultation.
"We know how deeply our community cares about our coastal waterways, beaches and local environment and we thank everyone who took the time to review the project details and share their feedback," Cr Byrnes said.
"Independent consultants engineered both shortlisted options to meet strict NSW EPA standards and resolve past performance and reliability issues at the plant.
"Council's decision balances long-term environmental protection and operational resilience with financial responsibility for our ratepayers," he said.
Council's Director Engineering Tim Mackney said the selected concept design will upgrade ageing infrastructure and significantly improve the plant's day-to-day performance and resilience to natural events.
"Option 4 modernises the plant by adding a third aeration treatment tank, new inlet equipment, improved hydraulics, better operational controls, updated decant and filtration systems, an odour-control system, a 99kW solar array and aesthetic and noise improvements," Mr Mackney said.
"For the community, this means a far more reliable plant especially during heavy rain and busy holiday periods, consistently cleaner treated water that meets strict NSW EPA limits and strong protection for local creeks and coastal groundwater. This aligns closely with community feedback calling for long-term coastal resilience.
"Importantly, Option 4 delivers these strong environmental outcomes while keeping construction and ongoing running costs more affordable for ratepayers."
Mr Mackney said the upgraded plant would continue to release treated water into the existing dune disposal system.
"Either upgrade option would have continued to utilise the existing dune system; however, the upgraded plant will better protect the dune system through higher treatment quality and improved reliability," Mr Mackney said.
"A separate study has also been proposed to look at the long-term operation and sustainability of the dune disposal system, particularly considering potential climate change impacts.
"Once upgraded, the plant will also be far more adaptable if Council moves to different ways of releasing treated water in the future."
Council has worked closely with the Hastings Point WWTP Consultative Committee throughout the project. The independently chaired panel brought together 5 qualified local community representatives with backgrounds in civil engineering, environmental science, finance and governance, alongside Council staff.
The committee played a central role in shaping how the options were assessed, ensuring NSW EPA compliance was treated as a strict pass/fail requirement and giving higher weightings for environmental protection, community amenity and system resilience in the Multi-Criteria Analysis.
Feedback from the August–September 2026 public exhibition, which attracted 78 survey responses and 8 detailed written submissions, was also reviewed by the committee and provided to Councillors ahead of last week's vote.
Next steps
With a preferred concept option now confirmed, the project will move into the planning approvals phase in early 2027. This includes environmental impact assessments and supporting studies, followed by NSW Government approval.
Detailed design and construction will follow from the second half of 2027.
Background
2024 initial assessment: Engineering firm GHD assessed 5 initial upgrade options in 2024, peer-reviewed by Beca Hunter H2O. That report went on public exhibition in May–June 2024.
February 2025 shortlist: Following community feedback, Council resolved in February 2025 to carry out deeper engineering investigations into 2 shortlisted designs: Option 4 (Advanced Intermittent Process) and Option 5 (Membrane Bioreactor).
2025–2026 technical studies and Consultative Committee: In June 2025, Council established the independently chaired Hastings Point WWTP Consultative Committee. Alongside the committee's work on the assessment criteria, Beca Hunter H2O completed specialist environmental studies, population and holiday load modelling, geotechnical investigations and noise and odour assessments.
August–September 2026 public exhibition: Council exhibited the draft concept designs on Your Say Tweed for 4 weeks, inviting feedback via an online survey and written submissions, alongside briefing local community associations, attending the Pottsville Community Association meeting and running pop-up stalls at local markets and events.
November 2026 Council decision: Ahead of Thursday night's vote, Councillors considered Beca Hunter H2O's finalised Concept Design and Options Assessment Report, strategic advice from the Hastings Point WWTP Consultative Committee and feedback gathered from the community during the August–September public exhibition.