Dunns Road Stage 1 upgrade update

Earthworks on Stage 1 of the Dunns Road upgrade, which started earlier this month, are progressing but are being affected by inclement weather and the impact of COVID-19 on supply and staffing

Wagga Wagga City Council Director Projects Silas Darby is confident that despite these impacts the completion of Stage 1 will occur in December 2022.

Road Plant Ahead sign

The first stage of the upgrade involves three phases.

Phase 1 – Upgrading of the stormwater drainage. This work has been completed ahead of the program to minimise the damage to the road caused by expected high rainfall events - COMPLETED

Phase 2 – Earthworks which started in early May 2022 and involve removing existing top layers of the road and then replacing these layers using GPS enabled graders - UNDERWAY

Phase 3 – Sealing the entire length of Dunns Road - PENDING

Mr Darby said Stages 2 and 3 of the road upgrade rely on elements determined by external agencies.

Dunns Road Sign

Stage 2 of the upgrade will see Council working with Transport for NSW to construct a right-hand turning lane at the Olympic Highway and Dunns Road intersection.

Stage 3 of the upgrade is construction of a roundabout at the Holbrook Road and Dunns Road intersection and is subject to receiving black spot funding.

The project is funded by the Australian Government and Wagga Wagga City Council.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.