As part of North East Link Project (NELP) works, the Eastern Freeway will be closed between Bulleen Road and Doncaster Road from 10:00pm Friday 27 March until 5:00am Monday 30 March.
This closure will enable NELP to complete critical works, including the installation of new flyover lanes that will provide future entry to and exit from the North East Link tunnels.
What's expected
Delays of up to 60 minutes are expected during peak travel times. Motorists are encouraged to plan ahead, allow extra travel time and avoid the area where possible.
The closure will also impact the broader road network, with increased traffic expected on Doncaster Road, Tram Road, Manningham Road and Middleborough Road.
Electronic signs and detours will be in place to guide road users throughout the weekend.

Additional upcoming works - Springvale Road city bound on ramp
In addition to the freeway closure, widening works on the Springvale Road city bound on ramp will be undertaken during the following periods:
• 9:00pm Friday 27 March to 5:00am Monday 30 March
• 10:00pm Wednesday 8 April to 11:59pm Friday 24 April
• 9:00pm Friday 1 May to 5:00am Monday 4 May
These works will include:
• installing and adjusting temporary traffic barriers
• noise wall removal
• removal of existing kerb and asphalt
• earthworks and pavement construction
• relocation of existing drainage
• construction of a temporary site access into the work site from Junction Road Reserve

If you have any further queries regarding this closure or other NELP associated works, call 1800 105 105 or visit bigbuild.vic.gov.au/projects/north-east-link-program.