EnergyConnect Scheduled Maintenance

Wentworth Shire

Elecnor Australia has notified Wentworth Shire Council of upcoming scheduled maintenance activities as part of the EnergyConnect project. This work is essential to connecting the electrical grids of New South Wales, South Australia, and Victoria to improve national energy reliability.

Work Overview

Crews will be replacing the overhead heavy earth wire (OHEW) on the 220kV line spanning from the Buronga Substation in NSW to the Red Cliffs Substation in Victoria.

Schedule and Hours

Work is scheduled to occur between Friday 10 April and Saturday 18 April 2026.

While standard construction hours are typically restricted, this activity will operate under extended "Out of Hours" timing to complete the work safely:

  • Monday to Sunday: 7:00am - 7:00pm (including Public Holidays).

What to Expect

  • Traffic Delays: Motorists using the Sturt Highway and Arumpo Road should prepare for traffic control measures and potential delays of up to 15 minutes.
  • Heavy Equipment: Residents may notice elevated work platforms (up to 70 metres), heavy trucks, and light vehicles in the area.
  • Impact Management: The project team is implementing noise-reduction measures, maintaining machinery, and using water carts to suppress dust on unsealed roads.

Project Contact Information

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.