New Pathway to Electrify Industrial Heat at Scale Demonstrated

The Australian Renewable Energy Agency (ARENA) will provide funding to support Australia's largest demonstration of industrial heat electrification, helping to validate the role of thermal energy storage in reducing fossil fuel use in energy-intensive industries and paving the way for similar projects in other sectors.

The project is being delivered at Rio Tinto's Yarwun alumina refinery near Gladstone, Queensland and will be one of the first large-scale demonstrations of thermal energy storage for industrial process heat globally.

Industrial process heat is extremely challenging to decarbonise. Heavy industries such as alumina refining rely on large volumes of continuous, high-temperature steam that has traditionally been produced using fossil fuels. Thermal energy storage has emerged as a promising option where low-cost electricity is stored as heat and used to produce a continuous output of steam for refinery operations, reducing reliance on fossil fuel usage.

ARENA's funding for the project will be provided in stages, with an initial $3.6 million to complete front-end engineering and design work. Following successful completion of that study, ARENA will provide up to $38 million for deployment. ARENA has also approved up to $33.3 million in conditional contingency support, which would only be made available in defined circumstances to manage specific project risks, including cost overruns and electricity costs.

ARENA CEO Darren Miller said technologies such as thermal energy storage need to be tested in real large-scale operating environments before they can be adopted more broadly across Australian industry.

"Industrial heat remains one of the toughest decarbonisation challenges facing heavy industries," Mr Miller said.

"This project will test whether thermal energy storage can provide a practical pathway to lower emissions from industrial heat in a real-world operating environment, where reliability, performance and integration are critical."

"Large industrial facilities such as Yarwun provide the scale, infrastructure and operating conditions needed to properly evaluate emerging technologies. Demonstrations like this will help build the evidence industry needs to make future investment decisions so the value of this project extends well beyond a single refinery."

The project will deploy a 30 MWt (discharge) / 78 MWe (charge) / 360MWh Rondo Energy thermal energy storage unit at Yarwun, using low-cost electricity to charge a heat battery that can store energy and release it when needed to generate steam for industrial operations. It is expected to cut onsite emissions by around 67,000 tonnes of carbon dioxide each year.

Mr Miller said ARENA wants to work with industrial businesses and technology providers to develop the next generation of industrial heat projects.

"ARENA is looking to support further projects that can demonstrate thermal energy storage and other promising approaches to industrial heat electrification in Australian operating conditions.

"We encourage industrial businesses, technology providers and project developers with credible proposals to speak with us about how we may be able to help bring those projects forward."

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.