Upcoming works on Black Spur

black spur.JPG

To keep everyone safe on the Black Spur, VicRoads need to undertake a program of tree removal and maintenance works starting in March.

Following a series of serious incidents that involved trees falling on the Spur, the Department of Transport engaged an independent arborist to asses all trees within 20 metres of the centreline of the road, between Healesville and Narbethong.

This assessment has identified that 98 trees are considered unstable and need to be removed, while a further 28 need to have large limbs pruned to maintain public safety.

Stage one works

The Spur is planned to be closed between: 9:30am - 3:30pm on:

  • Monday 16 - Thursday 19 March
  • Monday 23 - Thursday 26 March

Stage two works

The Spur is planned to be closed between 9:30am - 3:30pm on:

  • Monday 20 - Thursday 23 April
  • Monday 27 - Thursday 30 April
  • Monday 4 - Thursday 7 May
  • Monday 11 - Thursday 14 May

Community drop in sessions

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.