Council Moves to Restore Vera Street in Helensburgh

It's anticipated that works will begin in late January

Image: The site following the 2024 flood disaster

Works to restore two-way access to a key intersection within the Helensburgh Train Station precinct will soon get underway after Wollongong City Council awarded the tender for the reconstruction of road embankments at Vera Street and Old Station Road.

The tender is for a third phase of works at the site to restore road embankments that collapsed due to a declared natural flood disaster in 2024, exacerbating damage that first occurred during a previous declared disaster event in 2022.

Sydney Water carried out emergency remedial works in the immediate aftermath of the event to stabilise underground assets exposed by the embankment failure, allowing Council to re-open the road with one-way road access to the train station.

Following a second phase of interim works undertaken by Council, the tender awarded by resolution at the most recent meeting of Council (16 November) covers works to reinstate the road width at the Vera Street-Old Station Road intersection and restore two-way access.

Lord Mayor of Wollongong Councillor Tania Brown said Council was pleased to be progressing essential works at a site presenting numerous challenges.

"It's been a challenging project to navigate given the potential impacts on underground services, which required reviews and approvals from other agencies and governing bodies, including the adjacent landowner Crown Lands," Cr Brown said.

"We've taken a long-term, phased approach to work through the approvals and carry out detailed investigations and Geotech modelling to ensure we're rebuilding a more resilient asset. It's an approach we've taken to rebuilding a large amount of infrastructure affected by the flood events we've endured in recent years.

"We appreciate the patience of the community as we've worked through this process, and we're pleased to award the tender to complete an important piece of flood recovery work."

Works will include rebuilding the existing headwall, a rock dissipation platform, cleaning out the culvert and stabilising the embankment. New traffic signs, line marking and guardrails will also be installed.

It is currently anticipated that works will begin in mid-late January 2027.

The restoration works are jointly funded by Council and the NSW Essential Public Assets Restoration Natural Disaster Grant Program. This grant program is funded jointly by the NSW and Australian Governments under Disaster Recovery Funding Arrangements to help councils to restore essential public assets damaged by declared natural disasters.

To stay updated on the works, visit Vera and Wilson Streets Helensburgh project page

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.