Mt Barker Project Reaches Major Milestone

SA Gov
Huge girders delivered for structure set to improved traffic flow in rapidly-growing pocket of South Australia.

Aerial images of the new three-laned bridge at Mount Barker above the South Eastern Freeway. Images: DIT

The last of 12 84-tonne girders to support a new three-laned bridge at Mount Barker above the South Eastern Freeway have been put in place, marking a major milestone for the project.

The new bridge, which is being constructed immediately west of the existing bridge, will provide three northbound traffic lanes and an on-road bike lane, delivering greater traffic flow for motorists and safety and connectivity improvements for cyclists.

The existing bridge will be converted to accommodate three southbound lanes, while traffic signals and lighting will be installed at the interchange to improve safety.

A large truck with a specialised "jinker" trailer – designed to transport long pieces of equipment – was used to transport the 38m-long girders from the precast facility.

The Mount Barker Interchange upgrade is being delivered concurrently with works at Verdun Interchange. Both projects are being funded by a $150 million partnership between the State and Federal governments through respective commitments of $30 million and $120 million.

The ongoing Verdun works will deliver access to and from the Freeway in all directions. The interchange does not currently allow motorists driving from Mount Barker to Hahndorf to exit, while eastbound motorists – those wanting to travel between Hahndorf and Mount Barker – cannot easily access the Freeway.

The upgrade will deliver a new eastbound entry ramp towards Mount Barker, and a new westbound exit ramp. The exit ramp will cross under the existing westbound entry ramp before connecting with a new roundabout at the junction of Mount Barker Road and Silver Road.

The new bridge over the westbound exit ramp at Verdun will be more than 13m long and 7m wide, supported by 29 concrete piles and 12 bridge planks.

More than 50,000 vehicles travel from Verdun into the city each day and more than 30,000 vehicles travel across the Mount Barker interchange between Littlehampton and Mount Barker.

In the past five years there have been 19 casualty crashes at the Mount Barker Interchange and seven at the Verdun Interchange.

The works are supporting approximately 260 full-time jobs during construction.

The upgraded interchanges are expected to open to the community in late 2027.

To find out more about the projects, visit South Eastern Freeway Interchange Upgrades .

/Public News. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).