- The Queensland Productivity Commission interim report into Canberra's EPBC laws unveils staggering time and cost impacts to Queenslanders.
- Report found environmental approvals were taking an average of 1,150 days, with delays costing Queensland up to $7.7 billion a year.
- Environmental offset arrangements predicted to inflate cost of new homes by up to $40,000.
- The Crisafulli Government will extend the Inquiry to July 2027 to allow assessment of 2025 EPBC changes that haven't yet commenced.
The Queensland Productivity Commission's interim report into Canberra's 2025 environmental legislation changes has revealed the true impact of the EPBC process, with delays and major cost impacts for infrastructure projects.
The Crisafulli Government commissioned a Queensland Productivity Commission review into the Federal Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), to determine the impacts on Queensland infrastructure delivery.
The interim report, released by the Queensland Productivity Commission today, has made some startling findings including:
- EPBC assessments have taken on average 1,150 days.
- Delay costs from EPBC Act requirements cost Queensland up to $7.7 billion in lost productivity each year.
- The cost of new vegetation management rules is costing Queensland agriculture up to $41 million a year
- Environmental offset requirements under the EPBC are adding up to $40,000 for homes in greenfield developments.
The independent Commission found Queensland has consistently had one of the highest rates of referrals under the EPBC Act, with Queensland projects also more likely to become controlled actions and therefore subject to rigorous assessments.
With a record $119 billion infrastructure delivery pipeline, for new roads, rail and bridges, the Queensland Productivity Commission interim report suggests the EPBC requirements mean Queenslanders will pay more and wait longer for projects.
It also puts additional costs onto new homes, pushing the dream of home ownership further from reach.
The Queensland Productivity Commission has made 12 interim recommendations aimed at removing duplication between the State and Federal Governments, including renewing and expanding Commonwealth-State assessment arrangements, better aligning offset schemes and using Queensland vegetation codes to streamline low-risk land-management activities.
These recommendations will now be considered by the Crisafulli Government as the Queensland Productivity Commission continues its Inquiry.
Given some major elements of the EPBC changes are yet to commence, the commission will be given a three-month extension to conduct the inquiry to July 2027 and receive more valuable feedback from industry on the full impact of the 2025 reforms.
Treasurer David Janetzki said the interim report showed Canberra's green tape was costing Queenslanders more and delaying construction for new homes and infrastructure.
"Queenslanders should not have to choose between strong environmental protection and getting homes, infrastructure and essential services built on time," Treasurer Janetzki said.
"This independent report shows the system was already imposing extraordinary delays and costs for farmers, regional communities, homebuyers and businesses, and the Federal Government's 2025 changes risk adding another layer of uncertainty.
"At a time when Queenslanders need more homes, more infrastructure and fewer costs, we'll be looking closely at these 12 recommendations to play our part in reducing impacts on Queenslanders – we also ask Canberra to do the same."