Construction update
Work is continuing steadily with progress across the site. Milestones this month include:
Sports courts
The walls and ceiling of the amenities area is complete. Work on the outside of the building is moving along well. The middle layer of the exterior panels is finished on the north side and almost finished on the south. The metal cladding on the northern side is starting to go up. Inside the sports courts, work is continuing to install the ceiling. Installation of rooftop solar panels is well underway.
Warm water pool and spa, quiet studio and consult suites
Work is continuing on the internal and external walls. Installation of rooftop solar panels is well underway.
25m pool
Tiling has started.
Level 2 plant room
Installation of mechanical and electrical equipment, including the electric heat pumps for the hot water supply, is progressing.
Fitness and gym spaces
The concrete slab structure for the upper-level plant room has been poured. Fit out of the amenities block is underway.