Kew Recreation Centre March 2026 Progress Report

Construction update

Work is continuing steadily with progress across the site. Milestones this month include:

Sports courts

The walls and ceiling of the amenities area is complete. Work on the outside of the building is moving along well. The middle layer of the exterior panels is finished on the north side and almost finished on the south. The metal cladding on the northern side is starting to go up. Inside the sports courts, work is continuing to install the ceiling. Installation of rooftop solar panels is well underway.

Warm water pool and spa, quiet studio and consult suites

Work is continuing on the internal and external walls. Installation of rooftop solar panels is well underway.

25m pool

Tiling has started.

Level 2 plant room

Installation of mechanical and electrical equipment, including the electric heat pumps for the hot water supply, is progressing.

Fitness and gym spaces

The concrete slab structure for the upper-level plant room has been poured. Fit out of the amenities block is underway.

WorkSafe Victoria charges against ADCO Group Pty Ltd

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.