Progress on Dunns Road upgrade

Wagga Wagga City Council is continuing work on the Dunns Road upgrade, with the road due to be completely sealed by the end of June 2022, weather permitting.

Council has finished improving the cross road drainage, and is now carrying out earthworks and applying road pavement.

A group of workmen standing beside an enormous concrete pipe
SERIOUS DRAINAGE: Council has been busy at Dunns Road installing concrete cross road drainage and carrying out earthworks ahead of applying road pavement. Council is expecting to have the road completely sealed by the end of June 2022, weather permitting.

Associate Director of Projects Silas Darby said a reduced speed limit of 80 km/h would be in place on the adjoining section of the Olympic Highway between 9.30am and 3.30pm until Monday 23 May 2022.

"The speed limit has been reduced on the Olympic Highway between Dunns Road and the Old Olympic Highway at Kapooka while we're working," Mr Darby said.

"The reduced speed limit applies to both northbound and southbound lanes.

"We're using heavy transport to move material from our Kapooka stockpile site, which is alongside the Olympic Highway, to Dunns Road, so we're asking road users to drive slowly and be aware of trucks turning."

An enormous concrete pipe laying in the ground
SWITCH TO CONCRETE: Council replaced the old corrugated spun-metal culverts with concrete pipes and concrete box culverts.

Mr Darby said Council was currently midway through stage 1 of the upgrade.

"Right now, we're upgrading the existing 2.8-kilometre sealed section and sealing the remaining 2.2 kilometres of unsealed road," Mr Darby said.

"As long as the weather remains fine, we're aiming to have this finished by the end of June."

The second stage of the upgrade will see Council working with Transport NSW to construct a right-hand turning lane at the Olympic Highway and Dunns Road intersection.

Stage 3 of the upgrade, construction of a roundabout at the Holbrook Road and Dunns Road intersection, will be subject to receiving black spot funding.

Two men working on an enormous concrete box culvert
EARTHWORKS: A large concrete box culvert will aid the cross road drainage of Dunns Road.

The project is expected to be completed by December 2022.

The Dunns Road upgrade project is funded by the Australian Government ($5.8 million) and Wagga Wagga City Council ($2.5 million).

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.