Works will begin with the removal of the existing play equipment, which will be repurposed for other community uses within Eugowra. Landscaping works will then commence, with the new amenities building scheduled to arrive on site in late August or early September, followed by the installation of new play equipment.
Construction hours will be during the week and some weekends (Saturday only):
- Monday to Friday: 7am - 6pm
- Saturday: 8am - 1pm
The project is expected to be completed in early November 2026 and will deliver a revitalised, safe and welcoming space for residents and visitors to enjoy, while supporting community wellbeing and reflecting the resilience of the Eugowra community.
To keep updated with the project, register for Have Your Say Cabonne and follow the project by clicking the button below.