SYDNEY, Wednesday 1 July 2026 — The proposal for the 'Project Ares' data centre in remote Northern Territory, which would be powered by off-grid gas and renewables, has prompted renewed calls from Greenpeace for an urgent moratorium, citing serious concerns about emissions and environmental harm.
The application for the project under the EPBC Act reveals the gas-fired generation for the project would be approximately 1,038MW at full build-out, which would more than double the NT's current gas-fired generating capacity.
A recent report by Greenpeace Australia Pacific and independent expert Ketan Joshi, Energy Vampires: the AI data centres draining Australia, revealed how the frenzied rollout of AI data centres in Australia is set to derail the renewable energy transition, entrench gas and turbocharge climate pollution.
Solaye Snider, Campaigner at Greenpeace Australia Pacific, said: "Proposals like Project Ares, which would have significant off-grid gas powered generation and emissions, should not be moving along while there are still zero binding regulations to limit the impacts of AI data centres on our communities and environment.
"This hyperscale project proposes massive new off-grid gas infrastructure, making a mockery of the Federal Government's unenforceable 'expectations' that data centres will cover their own power use with renewables. Communities will pay the price for the data centre industry's endless hunger for energy at any cost.
"This proposal also raises serious questions about where this new gas would come from. Could it come from fracking the Beetaloo? Communities deserve to have the full picture before this project is approved.
"The Australian Government is asleep at the wheel when it comes to the rapid roll-out of AI data centres. We need an urgent moratorium on the construction and approval of new data centres, so our government can take appropriate time to legislate the regulations and safeguards we so desperately need."