Canowindra Precinct Upgrades

swinging bridge concept.PNG

Cabonne Council contractors will be commencing works on the Swinging Bridge Precinct.
Phase 1 - includes installation of a new shared pathway from Finns Lane to the Swinging Bridge. The construction period is approximately three (3) weeks duration and will commence the week of 16 October 2023.

The works include the construction of a new footpath approximately 170m in length and 3m wide and two (2) concrete pads to house picnic areas.

Phase 2 – includes installation of solar lighting, flood resistant seating and picnic furniture, additional tree planting and replacement of boundary fences. The construction period will happen in stages over the next six (6) months.

The works are funded under the Building Better Regions Fund (BBRF) and Resources for Regions (R4R) grant programs.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.