Flood protection project continues on Ouse Washes

The project to raise the Middle Level Barrier Bank to improve the Ouse Washes flood storage reservoir will maintain the standard of flood protection to more than 2,000 properties and 67,000 hectares of agricultural land.

As the washes are an internationally important habitat, construction work will continue during summer and early autumn to avoid disturbing breeding and over-wintering birds.

The improvement works underway will ensure compliance with recommendations made by the reservoir inspecting engineer. As such, it has a statutory deadline for completion under the Reservoirs Act 1975.

A reservoir inspection in 2020 set deadlines for the project with the physical construction to be completed by December 2022. Following this, there will be a further 2 years of maintenance works to establish grass cover to ensure the stability of the banks.

Demountable flood barrier at Welney

As part of the project and to comply with the Reservoirs Act, a robust demountable flood barrier is required at Welney where the Wash Road meets the Middle Level Barrier Bank.

Originally planned to take place during 2021, this work has been rescheduled for 2022. This is due to delays last year in the bank raising work caused by wet weather.

To complete the flood barrier construction it will be necessary to gain permission to close the Welney Wash Road/A1101 for 6 to 8 weeks in 2022.

A consultation with residents indicates that their preferred time for these works to be carried out is during the school summer holidays. See the report to the consultation.

Nicola Oldfield, Project Manager for the Environment Agency, said:

The construction works to refurbish the Ouse Washes flood storage reservoir remain on track to be completed by the end of 2022.

We are complying with recommendations from the reservoir inspecting engineer. The work when finished will help to ensure that people, land and buildings are protected from flood water escaping from the reservoir for years to come. The public can be assured that the reservoir remains in a safe condition while these works are ongoing.

We would like to thank the local community for their patience and understanding during this challenging complex programme of work which is taking longer than we originally predicted.

The work is being carried out in line with the government's coronavirus guidance with public footpaths along the crest of the Middle Level Barrier Bank diverted to maintain safety.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.